This Affects San Vicente Boulevard from Bringham to Barrington, Barrington to Gorham
Notice has been given for the upcoming repaving project of San Vicente Boulevard in Brentwood courtesy of The Brentwood Community Council’s newsletter. The prep work started on June 22 and will continue until June 28 on San Vicente between Bringham and Barrington and Barrington To Gorham. Please plan your work and recreational driving routes accordingly.
Mill prep dates:
6-22-23 thru 6-23-23 Mill prep on San Vicente Bl N Rdwy from Bringham Ave to Barrington Ave.
6-26-23 thru 6-27-23 Mill prep on San Vicente Bl N Rdwy from Barrington Ave to Gorham Ave.
6-26-23 thru 6-27-23 Mill prep on San Vicente Bl S Rdwy from Barrington Ave to Gorham Ave.
6-27-23 thru 6-28-23 Mill prep on San Vicente Bl S Rdwy from Bringham Ave to Barrington Ave.
The dates for the repaving itself go from June 28 to June 30 on San Vicente from Bringham to Barrington and Barrington to Gorham.
Paving dates:
6-28-23 thru 6-29-23 Pave on San Vicente N Rdwy from Bringham Ave to Barrington Ave.
6-28-23 thru 6-29-23 Pave on San Vicente Bl N Rdwy from Barrington Ave to
Gorham Ave.
6-29-23 thru 6-30-23 Pave on San Vicente Bl S Rdwy from Barrington Ave to Gorham Ave.
6-29-23 thru 6-30-23 Pave on San Vicente Bl S Rdwy from Bringham Ave to Barrington Ave.